Quality Control Measures of All-aluminum Alloy Formwork in High-rise Building Construction

[China Aluminum Industry Network] 1) Formwork builders and quality personnel are required to be familiar with design drawings, participate in drawing proofreading, and participate in the process of formulating the template processing plan, and be familiar with the template operation process.

2) Turn off the aluminum mold factory. When the aluminum mold is manufactured and assembled in the factory, arrange the technicians to go to the factory for inspection and acceptance. As far as possible, some problems encountered during the assembly of the site will be solved at the factory to avoid returning to the factory for processing. Duration.

3) Make a good presentation of construction technology and workers' training. Workers entering the field will be provided with detailed technical disclosure by construction technicians so that each team leader and workers will be familiar with process and quality requirements.

4) During the production process, construction technicians and quality inspectors must adhere to the site, supervise and instruct the entire process of the construction process, identify problems and carry out rectification in a timely manner to ensure good technology and quality.

5) Strict process inspection and acceptance. Each team must set the quality inspection team for each team. After each type of module construction is completed, it must be inspected by the team itself. After the requirements are met, the construction staff will perform a full review of the components one by one, and the full-time quality inspector will be notified later. Accept the template project and make a record.